1221 12th St NW- Three weeks left
At the 12th St project, we're working basically around the clock to finish in the next three weeks. For the majority of a renovation project, you are held back a bit in terms of speed because you're often relying on other people to finish their job before you can finish yours. For example, the sheetrock guys are waiting for the electrician, who comes after the HVAC, who comes after the plumber, who comes after the framers, and so on. However, after the sheetrock is up and sanded, there's really no one left in the way. The trim guys can work at the same time as the painters, exterior carpenters, concrete workers and tile men. Even the plumber and electrician can come back at any point. This is the point we've finally reached. We're working hard to finish before mid-April so buyers get a chance to take the $8,000.00 tax credit before the end of the month.