The framing is moving along quickly at the new condo building, and we're very close to topping out. The third floor is framed, and all that's left is the small loft space above. Our plan is to start framing out the interior walls and begin the plumbing in the basement next week.
Here's the current progress. We had really high winds last night and it pulled of some of the Tyvek on the top left side. This isn't a problem- the housewrap is just loosely held in place at this point. Next week we'll come back with scaffolding and seal all of the seams and make sure the building is tightly protected from the elements.